JIVO Energy has been engaged in the Diapaga 2 MWp Solar Photovoltaic Project in Burkina Faso since 2022, under a turnkey contract for the construction of a 2 MWp photovoltaic solar power plant, including one year of Operations & Maintenance (O&M). Due to security challenges in the region have kept the project on hold. Finally, discussions are ongoing to relocate the project to a safer zone, with preliminary studies pointing to Ziga as the opted location, involving ground-mounted solar panels, associated substation infrastructure, and connection to the national grid managed by SONABEL. |
Technology
Ground-Mounted Solar PV - Grid-Connected
Client
SONABEL
Capacity
2 MWp
Year of Completion
2026 *
* Planned